Saturday 2 May 2009

LAN - ROME / wall2 definition and construction

Preparing the construction: having a number of different elements ready to be ‘cooked’ from grasshopper to rhino, checking that the surfaces defining each brick’s model were closed, and calibrating the surface to be milled on our physical bricks dimensions, checking in rhinocam the construction and exporting the construction file.

Construction: the cnc machine needed some calibration (we had some ‘invisible brick’ issue), but most of all everything needed a strong finishing process, to be done at Solido workplace.
Some photos here: http://livearchitecture.net/workshops/?p=162

Then it was time for PechaKucha night!

0 comments: